Complete Sewer Connection Service
|
Stages in residential sewer connection:
- Receipt of Notice to Proceed
from Wastewater District (or installation of District connection box at property line).
- Monroe County Health
Department permit acquisition for the removal, abandonment or conversion of existing onsite sewage treatment system.
- Monroe County Building Department permit acquisition for the installation of sewer lateral from building to District
supplied connection box.
- Installation of lateral piping originating at or near the building discharge and terminating
at or near District connection box.
- Inspection of lateral pipe by Monroe County plumbing inspector.
- Visual
inspection of lateral pipe by Wastewater District.
- "Dry" connection of lateral pipe to District connection
box.
- Receipt of "30 Day Letter" from Wastewater District setting connection timeline and instructing that
treatment system is operable and ready to accept wastewater.
- Connection of installed lateral to building discharge.
- Final
inspection by Monroe County Building Department of building tie-in.
- Final inspection by Wastewater District of on-line
connection.
- Removal, abandonment or conversion of existing onsite sewage treatment system.
- Final inspection
by Monroe County Health Department.